| 7946 |
— |
Dug Well |
Puntland Ministry of Energy Minerals and Water |
April 4, 2022 |
Sanaag |
laasqoray |
Durduri |
0.5 |
Lasqoray concern |
05/08/05 |
Durduri dugwell |
— |
11.2962838 |
48.5848273 |
-10.0 |
— |
1 |
— |
rural urban |
yes |
— |
Yes |
— |
1200 |
500 |
100 |
3000 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
6.0 |
3.0 |
6.0 |
15.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
50.0 |
Galvanised Steel |
420.0 |
— |
2 |
1 |
yes |
2 |
9.0 |
Submersible Pump |
Grunfos |
— |
5.0 |
Solar |
— |
— |
— |
— |
fair |
The yield of dugwell is low
There is no good storage water. |
no |
— |
34.4 |
7.9 |
2230.0 |
1117.0 |
— |
Communal |
no |
— |
— |
— |
no |
— |
no |
— |
— |
— |
Puntland MoEMW |
04/01/21 |
Installation of solar power system |
1: Construction of new elevated water tank
2: Generator.
3: Replacement of main raising pipes and submersible pump.
4: Construction of caretaker room. |
— |
— |
| 7927 |
— |
Borehole |
Puntland Ministry of Energy Minerals and Water |
April 4, 2022 |
Sanaag |
laasqoray |
Ceelaayo |
5.0 |
Red Crescent Society for United Arab Emirates |
01/05/13 |
Ceelaayo borehole |
— |
11.2238021 |
48.9195977 |
-10.0 |
— |
1 |
— |
rural urban |
yes |
— |
Yes |
— |
1500 |
600 |
— |
2000 |
1.0 |
— |
40.0 |
gi |
10.0 |
20.0 |
10.0 |
4.0 |
— |
2.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
40.0 |
Galvanised Steel |
5200.0 |
— |
4 |
2 |
no |
— |
— |
Submersible Pump |
Lowara |
— |
33.0 |
Hybrid - Solar/Generator |
Perkins |
40.0 |
— |
13.5 |
poor |
Pipelines is in a bad condition |
no |
— |
35.3 |
8.4 |
2360.0 |
1488.0 |
— |
Communal |
yes |
01/01/20 |
4 |
2 |
no |
— |
no |
— |
— |
— |
CARE Somalia |
01/05/20 |
Construction of kiosks
Rehabilitation of water tank
Submersible pump and a Generator |
1.Replacement of supply system into a PVC
2.Another elevated water tank, because the current water tank can''t supply fully
3.wire Fencing of the solar system and the Generator room.
4. Five kiosks.
5.Rehabilitation of the Solar panels
6. Another water tank for the Agricultural use,
N.B
because the care taker of the borehole and the fuel of the Generator, gets an income from the Agriculture keeps running the system. |
— |
— |
| 8033 |
— |
Borehole |
Somaliland MoWRD |
April 4, 2022 |
Sool |
taleex |
Sarmaanyo |
1.0 |
USAID |
01/05/16 |
Sarmaanyo borehole 1 |
— |
9.4839422 |
47.987448 |
894.0 |
— |
2 |
— |
rural |
yes |
— |
Yes |
— |
0 |
4000 |
0 |
6000 |
0.0 |
— |
240.0 |
pvc |
8.0 |
234.0 |
4.0 |
4.0 |
6.0 |
1.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
37.0 |
Galvanised Steel |
150.0 |
0 |
0 |
5 |
no |
— |
— |
Submersible Pump |
Laura |
15.0 |
234.0 |
Hybrid - Solar/Generator |
Perkins |
45.0 |
EMT2-6350M |
350.0 |
good |
This borehole is for animal only and the system is good |
no |
— |
35.0 |
7.4 |
1500.0 |
1800.0 |
— |
Communal |
yes |
01/01/19 |
0 |
0 |
no |
— |
no |
— |
— |
— |
USAID |
01/01/20 |
Solar system installed in this borehole by USAID and implemented by ARA |
It requires fence to protect the borehole and maintai the water reservior and animal troughs as well |
— |
— |
| 7138 |
— |
Dug Well |
Puntland Ministry of Energy Minerals and Water |
April 3, 2022 |
Sool |
taleex |
Carooley |
0.0 |
Community |
03/04/06 |
Carooley Dug well |
— |
8.85608 |
48.1468823 |
577.0 |
— |
1 |
— |
rural urban |
yes |
— |
Yes |
— |
3150 |
1220 |
120 |
2000 |
0.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
7.0 |
3.0 |
4.0 |
15.0 |
— |
3.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
20.0 |
PVC |
2800.0 |
50 |
6 |
6 |
yes |
10 |
8.0 |
Submersible Pump |
Lowara |
1.5 |
6.0 |
Hybrid - Solar/Generator |
Parkins |
30.0 |
— |
— |
fair |
Needed full rehabilitation |
yes |
Colorless and odorless |
34.5 |
7.1 |
6080.0 |
4073.0 |
— |
Communal |
yes |
03/04/77 |
4 |
2 |
no |
— |
yes |
— |
— |
— |
— |
— |
— |
1. Rehabilitation pipelines
2. Rehabilitation of elevated water tank |
— |
— |
| 7920 |
— |
Borehole |
Somaliland MoWRD |
April 3, 2022 |
Sool |
taleex |
Godaale |
1.0 |
UNICEF |
03/04/15 |
Godaale borehole |
— |
9.0939633 |
47.9156598 |
670.0 |
— |
1 |
— |
rural |
yes |
— |
Yes |
— |
5500 |
80000 |
500 |
9000 |
0.0 |
— |
150.0 |
pvc |
8.0 |
114.0 |
15.0 |
20.0 |
0.0 |
0.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
18.0 |
Galvanised Steel |
1000.0 |
5000 |
0 |
4 |
yes |
80 |
40.0 |
Submersible Pump |
Perkins |
8.0 |
3.0 |
Hybrid - Solar/Generator |
Laura |
30.0 |
— |
300.0 |
good |
The system is working well |
no |
— |
29.0 |
7.4 |
2400.0 |
1700.0 |
— |
Communal |
no |
— |
— |
— |
no |
— |
no |
— |
— |
— |
NRC |
03/02/18 |
The agency implemented Solar system installed at borehole and replaced pipes |
The pipes are need to replace because the have been working 4 years and now they are leaking the water. The animal troughs are broken while water tank is damaged and releasing water as well. All the require to replace, maintain and Construction to new once |
— |
— |
| 7905 |
— |
Dug Well |
Puntland Ministry of Energy Minerals and Water |
April 3, 2022 |
Sool |
las_caanood |
Duudshabeel |
0.0 |
Community |
03/04/92 |
Duudshabeel dug well |
— |
8.9388005 |
47.4434569 |
522.0 |
— |
1 |
— |
rural |
yes |
— |
Yes |
— |
500 |
— |
— |
850 |
0.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
10.0 |
— |
3.0 |
7.0 |
— |
2.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
25.0 |
PVC |
120.0 |
— |
1 |
2 |
yes |
3 |
6.0 |
No Pump |
— |
— |
— |
— |
— |
— |
— |
— |
fair |
Poor of water supply |
yes |
Colorness and this source needs full water quality testing |
28.2 |
7.8 |
2500.0 |
1675.0 |
— |
Communal |
no |
— |
— |
— |
no |
— |
no |
— |
— |
— |
Agency not specified |
03/04/18 |
1. Construction of ground water tank
2. Construction of koisks |
1. Rehabilitation of dug well |
— |
— |
| 7127 |
— |
Borehole |
Puntland Ministry of Energy Minerals and Water |
April 3, 2022 |
Sool |
taleex |
Qalwo |
2.0 |
UNICEF |
03/04/20 |
Qalwo BH |
— |
8.9263499 |
48.2875784 |
513.0 |
— |
1 |
— |
urban rural |
yes |
— |
Yes |
— |
2450 |
1200 |
— |
2300 |
0.0 |
— |
200.0 |
pvc |
8.0 |
23.0 |
7.4 |
12.0 |
— |
6.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
40.0 |
PVC |
2000.0 |
— |
3 |
3 |
yes |
20 |
8.0 |
Submersible Pump |
Lowara |
11.0 |
180.0 |
Generator |
Parkins |
45.0 |
— |
— |
good |
— |
no |
— |
— |
— |
— |
— |
— |
Communal |
yes |
17/08/20 |
4 |
0 |
yes |
0.1 |
yes |
— |
— |
— |
— |
— |
— |
1. Extension pipelines
2. Construction of new kiosks
3. Water supply |
— |
— |
| 7895 |
— |
Borehole |
Somaliland MoWRD |
April 3, 2022 |
Sool |
taleex |
Caroweyn |
4.5 |
Somaliland MoWRD |
01/01/12 |
Carooley misirta |
— |
8.8819268 |
48.1712575 |
473.0 |
— |
1 |
— |
rural |
yes |
— |
Yes |
— |
12000 |
6000 |
0 |
8000 |
0.5 |
— |
113.0 |
pvc |
11.0 |
50.0 |
40.0 |
8.0 |
0.0 |
0.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
40.0 |
Galvanised Steel |
4500.0 |
2400 |
3 |
4 |
yes |
35 |
40.0 |
Submersible Pump |
Perkins |
45.0 |
3.0 |
Hybrid - Solar/Generator |
Perkins |
45.0 |
BR-Moow |
300.0 |
good |
Good |
no |
— |
28.0 |
7.2 |
2600.0 |
1800.0 |
— |
Communal |
yes |
03/04/12 |
5 |
2 |
no |
— |
no |
— |
— |
— |
KAALO Relief and Development |
01/01/19 |
Constructed water tank and solar system installation |
Change pipe of the borehole and and need a generator |
— |
— |
| 7772 |
— |
Dug Well |
Puntland Ministry of Energy Minerals and Water |
April 3, 2022 |
Sool |
las_caanood |
Xudun |
0.0 |
Community |
03/04/07 |
Xudun dug well |
— |
9.1538636 |
47.4780043 |
599.0 |
— |
2 |
— |
urban |
yes |
— |
Yes |
— |
4500 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
10.0 |
— |
5.0 |
12.0 |
— |
3.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
86.0 |
PVC |
1500.0 |
50 |
10 |
0 |
yes |
20 |
6.0 |
Submersible Pump |
Grandfoss |
1.2 |
3.0 |
Hybrid - Solar/Generator |
— |
5.0 |
— |
8.0 |
fair |
— |
yes |
Colorless and odorless |
29.5 |
7.5 |
4500.0 |
3015.0 |
— |
Communal |
yes |
03/04/89 |
4 |
3 |
yes |
0 |
no |
— |
— |
— |
DRC |
03/04/22 |
1. Construction of elevated water tank |
1. Rehabilitation of generator
2. Extension pipelines
3. Rehabilitation of dug well. |
— |
— |
| 7199 |
— |
Borehole |
Puntland Ministry of Energy Minerals and Water |
April 3, 2022 |
Sanaag |
laasqoray |
Laasqoray |
1.0 |
Somaliland MoWRD |
03/04/18 |
Laasqoray borehole |
— |
11.1799066 |
48.2423582 |
-3.0 |
— |
3 |
— |
rural |
yes |
— |
Yes |
— |
600 |
300 |
— |
1200 |
0.5 |
— |
22.0 |
pvc |
8.0 |
21.0 |
5.0 |
8.0 |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
— |
Concrete/Masonry tank |
— |
Galvanised Steel |
50.0 |
— |
1 |
2 |
yes |
3 |
6.0 |
Submersible Pump |
Lowara |
— |
— |
Solar |
— |
— |
— |
— |
poor |
Distribution pipes are rusted.
|
no |
— |
34.6 |
8.1 |
2810.0 |
1400.0 |
— |
Communal |
no |
— |
— |
— |
yes |
0.03 |
yes |
— |
— |
— |
Community_e |
09/09/20 |
Construction of animal water troughs |
1: Pipes
2: Tools such as pipe accessories.
3: Construction of new borehole that has a less salinity |
— |
— |